TABLE OF CONTENTS

 

Executive Summary   I

1.       INTRODUCTION   1

2.       AIR QUALITY   4

3.       NOISE   9

4.       LANDSCAPE AND VISUAL   13

5.       WASTE MANAGEMENT   14

6.       SITE INSPECTION   15

7.       ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE   16

8.       IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURES   17

9.       FUTURE KEY ISSUES   18

10.     Conclusions   19

 

 

FIGURES

 

Figure 1                 Project General Layout

Figure 2                 Air and Noise Monitoring Locations

 

 

LIST OF APPENDICES

 

Appendix A

Construction Programme

Appendix B

Project Organization Chart

Appendix C

Action and Limit Levels for Air Quality and Noise

Appendix D

Calibration Certificates of Monitoring Equipment

Appendix E

Environmental Monitoring Schedules

Appendix F

Air Quality Monitoring Data

Appendix G

Noise Monitoring Data

Appendix H

Event Action Plans

Appendix I

Waste Flow Table

Appendix J

Environmental Mitigation Implementation Schedule (EMIS)

Appendix K

Weather and Meteorological Conditions during Reporting Month

Appendix L

Cumulative statistics on Environmental Complaints, Notifications of Summons and Successful Prosecutions

Appendix M

Summary of Site Audit in the Reporting Month

Appendix N

Outstanding Issues and Deficiencies

 

 

 


Executive Summary

 

 i.   The Civil Engineering and Development Department HKSAR has appointed MateriaLab Consultants Limited (MCL) to undertake the Environmental Team services for the Project and implement the EM&A works.

 

ii.   This Monthly EM&A report presents the environmental monitoring and audit works for the period between 1 September 2017 and 30 September 2017. As informed by the Contractor, major activities in the reporting month were:

 

ž   Excavation and laying of drainage pipe and manhole;

ž   Seawall modification works;

ž   Construction of tunnel box structure;

ž   D-wall construction works;

ž   Pumping test; and

ž   Excavation and ELS construction.

 

Breaches of the Action and Limit Levels

 

iii.   No Action / Limit Level exceedance was recorded for 24-hr TSP and construction noise at KTD1a, KTD2a and KER1b in the reporting month.

 

Complaint, Notification of Summons and Successful Prosecution

 

iv.   No environmental complaint, notification of summons and successful prosecution were received in the reporting month.

 

Reporting Changes

 

v.   There was no reporting change in the reporting month.

 

Future Key Issues

 

vi.   The key issues to be considered in the coming reporting month include:

 

Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, water quality, waste management and landscape and visual impact.